Pipe Line Construction and Irrigation Project

SAMUKH IRRIGATION PROJECT

Project Status: Completed

Project Description: 

  • 40 pivot connections;
  • Construction of DN1016-1220mm steel pipeline – 13.776 meters;
  • Welding of 1450 steel pipe joints;
  • Construction of OD250-710mm HDPE pipeline – 37.788 meters;
  • Welding of 3218 HDPE pipe joints;
  • Project duration – 58 days;
  • Quality control – PI Mitterfellner GmbH (Austria);
  • Testing – TÜV-SÜD (Germany);
  • Project commissioning – TÜV-SÜD (Germany);